Clovelly – Rear façade balcony upgrade – 2023

Demolition of existing rear access stairs to 4x units and construct newly built balconies

Works undertaken as follows

  • Demolition of existing structure 

  • New foundations and suspended slab including dividing structural walls

  • New aluminium windows and doors to the balcony 

  • Waterproofing and tiling 

  • Frameless balustrade system 

  • Render and painting 

Challenges 

We experienced minimal challenges however access for this job was a lot harder then anticipated. 

Year

12th of April 2023 

Milestones

Re-building a complete facade balcony upgrade within 14 weeks.